Hartwood Elementary School Rebuild

Growing Together, Building for the Future

At Stafford County Public Schools, we are dedicated to creating spaces where young minds can explore, learn, and thrive. The rebuild of Hartwood Elementary School marks an exciting new chapter for our district—one that honors the rich history of the Hartwood community while building a modern, safe, and welcoming environment for generations of students to come.

This new school is more than just classrooms and hallways. It is an investment in our children’s curiosity, a center for community connection, and a promise for a brighter tomorrow.

Opening Date

August 2028

Construction activities may sometimes disrupt surrounding properties and roadways.  Concerns or questions should be forwarded to Jon Cramer at cramerjs@staffordschools.net.

Proposed Location

Westlake Subdivision

map of proposed new Hartwood Elementary School building

 

 

 

 

 

 

 

 

Important Milestones

  • Preliminary Design: Complete
  • Land Acquisition: Complete
  • Final Design: Complete March 2026
  • Bidding: April 2026-May 2026
  • Construction Start: October 2026
  • Groundbreaking: October 20, 2026
  • Opening: August 2028

Analysis of Need

The current Hartwood Elementary School was originally constructed in 1963 with additions constructed in 1988 and 1993 and is long overdue for a replacement. Hartwood Elementary School has a current capacity of 649 students. This replacement school will add approximately 421 elementary school seats to alleviate projected crowding as identified in the latest student enrollment projections found within the Enrollment Accommodation Report (EAR). The Stafford County Board of Supervisors approved FY26-35 Capital Improvement Program (CIP) identifies this project’s completion to take place August 2028 (FY29). The new Hartwood Elementary School would be designed to be approximately 131,000 square feet in size and accommodate up to 1,070 students, addressing both current design and program capacity needs.

FY25 Capital Improvement Plan & 3R Infrastructure (adopted) 

Cost

Description Budget
Land/Property Acquisition $0
Design Services $2,202,4270
Construction $59,127,000
FF&E $7,111,000
Contingency $3,314,5730
Project Total $72,755,000