Rodney Thompson MS

Rodney Thompson Middle School Critical Systems and Restoration

At Stafford County Public Schools, we are dedicated to providing spaces where students can learn, grow, and thrive. The critical systems and restoration project at Rodney Thompson Middle School marks an important investment in our district, one that preserves and strengthens a valued school while ensuring a safe, comfortable, and reliable environment for the students and staff who learn and work there every day.

This project is more than upgraded equipment and building repairs. It is a commitment to the long-term health of our facilities, a foundation that lets teachers and students focus on learning, and a promise to care for the schools our community depends on for years to come.

Opening Date

August 2028

Construction activities may sometimes disrupt surrounding properties and roadways. Concerns or questions should be forwarded to Jon Cramer at cramerjs@staffordschools.net.

Location 

Rodney Thompson Middle School 
75 Wapole Street
Stafford, VA 22554

Project Summary

The Rodney Thompson Middle School Critical Systems and Restoration Project encompasses a comprehensive replacement of mechanical and critical systems, along with the restoration of interior finishes. Because work on mechanical and critical systems can negatively impact interior surfaces, the project is phased to first complete the mechanical replacements before proceeding with interior restoration. The critical systems component replaces outdated mechanical equipment that has exceeded its expected useful lift with more efficient and reliable systems. The interior restoration component will modernize and improve finishes throughout the building, enhancing both functionality and appearance. Together, these efforts will ensure the facility operates efficiently, safely, and comfortably. These upgrades are expected to be completed over multiple years.

Important Milestones

Preliminary Design: Complete
Final Design: November 2026
Bidding: October 2026 - November 2026 
Construction Start: Summer 2027
Opening: August 2028

Analysis of Need 

Rodney Thompson Middle School was originally constructed in 2000; as a result, significant portions of its mechanical systems and interior finishes have reached or exceeded their expected useful life. Taking a holistic approach to upgrading the facility’s critical systems simultaneously will streamline the maintenance and replacement cycles, improving overall operational efficiency. 

Cost

Description Budget

Land/Property Acquisition

$0
Design Services $1,441,000
Construction $14,407,000 
FF&E $0
Contingency $720,0000
Project Total $16,568,000